Unit Commitment

Unit commitment constraints are implemented for the Generator, Link and Process components. They are used to model the start-up and shut-down constraints, as well as ramping constraints. The implementation is based on Taylor (2015)1, and is supplemented with work by Hua et al. (2017)2 for a tightened linear relaxation.

Process formulation

Unless stated otherwise, all formulations shown for Link apply analogously to Process by replacing \((f,\hat f,F,l)\) with \((r,\hat r,R,m)\) and Link-* with Process-* in the constraint names.

Start-Up and Shut-down

For components marked as committable=True, new binary status variables \(u_{*,t} \in \{0,1\}\) are introduced, which indicate whether the component is running (1) or not (0) in period \(t\). This turns the model into a mixed-integer linear programme (MILP). The restrictions on the dispatch now enforce that the dispatch \(g_{n,s,t}\), \(f_{l,t}\) or \(r_{m,t}\) is only non-zero if the component is running, i.e. \(u_{*,t} = 1\):

Constraint Name
\(g_{n,s,t} \geq u_{n,s,t} \cdot \underline{g}_{n,s,t} \cdot \hat{g}_{n,s}\) Generator-com-p-lower
\(g_{n,s,t} \leq u_{n,s,t} \cdot \bar{g}_{n,s,t} \cdot \hat{g}_{n,s}\) Generator-com-p-upper
Constraint Name
\(f_{l,t} \geq u_{l,t} \cdot \underline{f}_{l,t} \cdot \hat{f}_{l}\) Link-com-p-lower
\(f_{l,t} \leq u_{l,t} \cdot \bar{f}_{l,t} \cdot \hat{f}_{l}\) Link-com-p-upper
Constraint Name
\(r_{m,t} \geq u_{m,t} \cdot \underline{r}_{m,t} \cdot \hat{r}_{m}\) Process-com-p-lower
\(r_{m,t} \leq u_{m,t} \cdot \bar{r}_{m,t} \cdot \hat{r}_{m}\) Process-com-p-upper

!!! note | Combined with Capacity Expansion

Unit commitment can be combined with capacity expansion for co-optimized investment and operational decisions:

///

If the minimum up time \(T_{\textrm{min_up}}\) is set, status switches are constrained to ensure that the component is running for at least \(T_{\textrm{min_up}}\) snapshots after it has been started up:

Constraint Generator-com-up-time:

\[\sum_{t'=t}^{t+T_\textrm{min_up}} u_{n,s,t'}\geq T_\textrm{min_up} (u_{n,s,t} - u_{n,s,t-1})\]

Constraint Link-com-up-time:

\[\sum_{t'=t}^{t+T_\textrm{min_up}} u_{l,t'}\geq T_\textrm{min_up} (u_{l,t} - u_{l,t-1})\]

The component may have been up for some periods before the optimisation period (n.optimize(snapshots=snapshots)). Start-ups before the start of snapshots count towards the sum in the constraint, so a component that started up less than \(T_{\textrm{min_up}}\) snapshots before snapshots is forced to remain up for the difference. If snapshots starts at the beginning of n.snapshots or no statuses have been computed before, the time before is reconstructed from the input attributes: the component was up for up_time_before snapshots, or, if down_time_before is positive, down for down_time_before snapshots (down_time_before takes precedence). If snapshots starts in the middle of n.snapshots, the statuses before snapshots are read from n.c.generators.dynamic.status as set by previous runs, and up_time_before/down_time_before apply to the time before n.snapshots. All snapshots before snapshots count as solved once n.c.generators.dynamic.status is set. Successive runs must therefore solve the snapshots in order, starting from n.snapshots[0], as n.optimize.optimize_with_rolling_horizon() does. The start-ups before snapshots are the positive differences of these statuses, which may be fractional with the linearized unit commitment.

At the end of snapshots the minimum up-time in the constraint is only enforced for the remaining snapshots, if the number of remaining snapshots is less than \(T_{\textrm{min_up}}\).

If the minimum down time \(T_{\textrm{min_down}}\) is set, status switches are constrained to ensure that the component is not running for at least \(T_{\textrm{min_down}}\) snapshots after it has been shut down:

Constraint Generator-com-down-time:

\[\sum_{t'=t}^{t+T_\textrm{min_down}} (1-u_{n,s,t'})\geq T_\textrm{min_down} (u_{n,s,t-1} - u_{n,s,t})\]

Constraint Link-com-down-time:

\[\sum_{t'=t}^{t+T_\textrm{min_down}} (1-u_{l,t'})\geq T_\textrm{min_down} (u_{l,t-1} - u_{l,t})\]

The component may have been down for some periods before the optimisation period. Shut-downs before the start of snapshots count towards the sum in the constraint in the same way as start-ups do for the minimum up-time.

Furthermore, two state transition variables for start-up (\(su_{*,t} \in \{0,1\}\)) and shut-down (\(sd_{*,t} \in\) {0,1}) are introduced to associate them with start-up and shut-down cost terms in the objective function. Start-up and shut-down costs can be static or time series varying per snapshot. The constraints are set so that the start-up variable is only non-zero if the component has just started up, i.e. \(u_{n,s,t} - u_{n,s,t-1} = 1\), and the shut-down variable is only non-zero if the component has just shut down, i.e. \(u_{n,s,t-1} - u_{n,s,t} = 1\):

Constraint Name
\(su_{n,s,t} \geq u_{n,s,t} - u_{n,s,t-1}\) Generator-com-transition-start-up
\(sd_{n,s,t} \geq u_{n,s,t-1} - u_{n,s,t}\) Generator-com-transition-shut-down
Constraint Name
\(su_{l,t} \geq u_{l,t} - u_{l,t-1}\) Link-com-transition-start-up
\(sd_{l,t} \geq u_{l,t-1} - u_{l,t}\) Link-com-transition-shut-down

These constraints are defined in the function define_operational_constraints_for_committables().

Mapping of symbols to component attributes
Symbol Attribute Type
\(g_{n,s,t}\) n.generators_t.p Decision variable
\(u_{n,s,t}\) n.generators_t.status Decision variable
\(su_{n,s,t}\) n.generators_t.start_up Decision variable
\(sd_{n,s,t}\) n.generators_t.shut_down Decision variable
\(\hat{g}_{n,s}\) n.generators.p_nom Parameter
\(\underline{g}_{n,s,t}\) n.generators_t.p_min_pu Parameter
\(\bar{g}_{n,s,t}\) n.generators_t.p_max_pu Parameter
\(T_{\textrm{min_up}}\) n.generators.min_up_time Parameter
\(T_{\textrm{min_down}}\) n.generators.min_down_time Parameter
\(T_{\textrm{up_time_before}}\) n.generators.up_time_before Parameter
\(T_{\textrm{down_time_before}}\) n.generators.down_time_before Parameter
Symbol Attribute Type
\(f_{l,t}\) n.links_t.p Decision variable
\(u_{l,t}\) n.links_t.status Decision variable
\(su_{l,t}\) n.links_t.start_up Decision variable
\(sd_{l,t}\) n.links_t.shut_down Decision variable
\(\hat{f}_{l}\) n.links.p_nom Parameter
\(\underline{f}_{l,t}\) n.links_t.p_min_pu Parameter
\(\bar{f}_{l,t}\) n.links_t.p_max_pu Parameter
\(T_{\textrm{min_up}}\) n.links.min_up_time Parameter
\(T_{\textrm{min_down}}\) n.links.min_down_time Parameter
\(T_{\textrm{up_time_before}}\) n.links.up_time_before Parameter
\(T_{\textrm{down_time_before}}\) n.links.down_time_before Parameter
Symbol Attribute Type
\(r_{m,t}\) n.processes_t.p Decision variable
\(u_{m,t}\) n.processes_t.status Decision variable
\(su_{m,t}\) n.processes_t.start_up Decision variable
\(sd_{m,t}\) n.processes_t.shut_down Decision variable
\(\hat{r}_{m}\) n.processes.p_nom Parameter
\(\underline{r}_{m,t}\) n.processes_t.p_min_pu Parameter
\(\bar{r}_{m,t}\) n.processes_t.p_max_pu Parameter
\(T_{\textrm{min_up}}\) n.processes.min_up_time Parameter
\(T_{\textrm{min_down}}\) n.processes.min_down_time Parameter
\(T_{\textrm{up_time_before}}\) n.processes.up_time_before Parameter
\(T_{\textrm{down_time_before}}\) n.processes.down_time_before Parameter

Ramping

Ramp rate limits can be defined for increasing output \(ru_{n,s,t}\) and decreasing output \(rd_{n,s,t}\). By default these are null and ignored. They must be provided per unit of the nominal capacity.

Note

When provided, ramping limits are also considered if they are not committable (committable=False), i.e. the component is not subject to start-up and shut-down constraints.

A unified ramp constraint formulation is used for all component types (fixed, extendable, and committable). For committable components, additional ramp limits at start-up \(rusu_{n,s}\) and shut-down \(rdsd_{n,s}\) can be specified. The general form for \(t \in \{1,\dots |T|-1\}\) is:

Constraint Dual Variable Name
\((g_{n,s,t} - g_{n,s,t-1}) \geq \left[ -rd_{n,s,t} \cdot u_{n,s,t} -rdsd_{n,s}(u_{n,s,t-1} - u_{n,s,t})\right] \hat{g}_{n,s}\) n.generators_t.mu_ramp_limit_down Generator-p-ramp_limit_down
\((g_{n,s,t} - g_{n,s,t-1}) \leq \left[ru_{n,s,t} \cdot u_{n,s,t-1} + rusu_{n,s} (u_{n,s,t} - u_{n,s,t-1})\right] \hat{g}_{n,s}\) n.generators_t.mu_ramp_limit_up Generator-p-ramp_limit_up
Constraint Dual Variable Name
\((f_{l,t} - f_{l,t-1}) \geq \left[ -rd_{l,t} \cdot u_{l,t} -rdsd_{l,t}(u_{l,t-1} - u_{l,t})\right] \hat{f}_{l}\) n.links_t.mu_ramp_limit_down Link-p-ramp_limit_down
\((f_{l,t} - f_{l,t-1}) \leq \left[ru_{l,t} \cdot u_{l,t-1} + rusu_{l} (u_{l,t} - u_{l,t-1})\right] \hat{f}_{l}\) n.links_t.mu_ramp_limit_up Link-p-ramp_limit_up
Constraint Dual Variable Name
\((r_{m,t} - r_{m,t-1}) \geq \left[ -rd_{m,t} \cdot u_{m,t} -rdsd_{m,t}(u_{m,t-1} - u_{m,t})\right] \hat{r}_{m}\) n.processes_t.mu_ramp_limit_down Process-p-ramp_limit_down
\((r_{m,t} - r_{m,t-1}) \leq \left[ru_{m,t} \cdot u_{m,t-1} + rusu_{m} (u_{m,t} - u_{m,t-1})\right] \hat{r}_{m}\) n.processes_t.mu_ramp_limit_up Process-p-ramp_limit_up

For non-committable components, \(u_{*,t} = 1\) for all \(t\), so the constraints simplify to:

  • \((g_{n,s,t} - g_{n,s,t-1}) \geq -rd_{n,s,t} \cdot \hat{g}_{n,s}\)
  • \((g_{n,s,t} - g_{n,s,t-1}) \leq ru_{n,s,t} \cdot \hat{g}_{n,s}\)

For extendable components, \(\hat{g}_{n,s}\) is replaced by the capacity variable \(G_{n,s}\).

Initial Conditions

The ramp constraints require knowledge of the previous snapshot's dispatch. At the first snapshot of the optimization horizon, this is handled as follows:

  • Rolling horizon optimization: When n.optimize(snapshots=...) starts after the first snapshot in n.snapshots and previous runs have set the dispatch, the dispatch and the commitment status from the previous snapshot are used automatically. With the linearized unit commitment the previous status may be fractional.
  • First snapshot of n.snapshots or no previous run: The p_init attribute specifies the initial dispatch level. For committable components, the initial status is determined by up_time_before > 0 (or down_time_before > 0, which takes precedence) and the initial dispatch is zero if the component was off. If p_init is not set (NaN), no ramp constraint is applied at the first snapshot. Non-committable components are always on; up_time_before and down_time_before are ignored for them.

These constraints are defined in the function define_ramp_limit_constraints().

Mapping of symbols to component attributes
Symbol Attribute Type
\(g_{n,s,t}\) n.generators_t.p Decision variable
\(G_{n,s}\) n.generators.p_nom_opt Decision variable
\(u_{n,s,t}\) n.generators_t.status Decision variable
\(\hat{g}_{n,s}\) n.generators.p_nom Parameter
\(\underline{g}_{n,s,t}\) n.generators_t.p_min_pu Parameter
\(\bar{g}_{n,s,t}\) n.generators_t.p_max_pu Parameter
\(ru_{n,s,t}\) n.generators_t.ramp_limit_up Parameter
\(rd_{n,s,t}\) n.generators_t.ramp_limit_down Parameter
\(rusu_{n,s}\) n.generators.ramp_limit_start_up Parameter
\(rdsd_{n,s}\) n.generators.ramp_limit_shut_down Parameter
\(g_{n,s,0}\) n.generators.p_init Parameter (initial dispatch)
Symbol Attribute Type
\(f_{l,t}\) n.links_t.p Decision variable
\(F_{l}\) n.links.p_nom_opt Decision variable
\(u_{l,t}\) n.links_t.status Decision variable
\(\hat{f}_{l}\) n.links.p_nom Parameter
\(\underline{f}_{l,t}\) n.links_t.p_min_pu Parameter
\(\bar{f}_{l,t}\) n.links_t.p_max_pu Parameter
\(ru_{l,t}\) n.links_t.ramp_limit_up Parameter
\(rd_{l,t}\) n.links_t.ramp_limit_down Parameter
\(rusu_{l}\) n.links.ramp_limit_start_up Parameter
\(rdsd_{l}\) n.links.ramp_limit_shut_down Parameter
\(f_{l,0}\) n.links.p_init Parameter (initial dispatch)
Symbol Attribute Type
\(r_{m,t}\) n.processes_t.p Decision variable
\(R_{m}\) n.processes.p_nom_opt Decision variable
\(u_{m,t}\) n.processes_t.status Decision variable
\(\hat{r}_{m}\) n.processes.p_nom Parameter
\(\underline{r}_{m,t}\) n.processes_t.p_min_pu Parameter
\(\bar{r}_{m,t}\) n.processes_t.p_max_pu Parameter
\(ru_{m,t}\) n.processes_t.ramp_limit_up Parameter
\(rd_{m,t}\) n.processes_t.ramp_limit_down Parameter
\(rusu_{m}\) n.processes.ramp_limit_start_up Parameter
\(rdsd_{m}\) n.processes.ramp_limit_shut_down Parameter
\(r_{m,0}\) n.processes.p_init Parameter (initial dispatch)

Linearization

The implementation is based on Hua et al. (2017)2 and relaxes the binary unit commitment variables to continuous variables:

\[u_{*,t},\quad su_{*,t},\quad sd_{*,t}\quad \in [0,1]\]

This allows for partial commitment states (generators can be partially on/off), making the problem more computationally tractable while losing some accuracy. To enable this, use:

n.optimize(linearized_unit_commitment=True)

Not compatible with modular components

Linearized unit commitment cannot be used with modular committable components and will result in a ValueError.

To tighten the relaxation, additional constraints are introduced that improve capturing the relationship between commitment status, ramping, and dispatch. At the first snapshot they use the previous dispatch and status as described in Initial Conditions and are skipped if the previous dispatch is unknown. The tightening is only applied to units whose start-up and shut-down costs are equal in every snapshot; for the other units the unit commitment variables are purely relaxed and a warning is logged. The added constraints limit the dispatch during partial start-up and shut-down, as well as ramping during partial commitment:

Constraint Generator-com-p-before:

\[\begin{gather*} g_{n,s,t-1} \leq rdsd_{n,s} \hat{g}_{n,s} \cdot u_{n,s,t-1} + (\bar{g}_{n,s,t} \hat{g}_{n,s} - rdsd_{n,s} \hat{g}_{n,s}) \cdot (u_{n,s,t} - su_{n,s,t}) \end{gather*}\]

Constraint Generator-com-p-current:

\[\begin{gather*} g_{n,s,t} \leq \bar{g}_{n,s,t} \hat{g}_{n,s} \cdot u_{n,s,t} - (\bar{g}_{n,s,t} \hat{g}_{n,s} - rusu_{n,s} \hat{g}_{n,s}) \cdot su_{n,s,t} \end{gather*}\]

Constraint Generator-com-partly-start-up:

\[\begin{gather*} g_{n,s,t} - g_{n,s,t-1} \leq (\underline{g}_{n,s,t} \hat{g}_{n,s} + ru_{n,s,t} \hat{g}_{n,s}) \cdot u_{n,s,t} - \underline{g}_{n,s,t} \hat{g}_{n,s} \cdot u_{n,s,t-1} \\ - (\underline{g}_{n,s,t} \hat{g}_{n,s} + ru_{n,s,t} \hat{g}_{n,s} - rusu_{n,s} \hat{g}_{n,s}) \cdot su_{n,s,t} \end{gather*}\]

Constraint Generator-com-partly-shut-down:

\[\begin{gather*} g_{n,s,t-1} - g_{n,s,t} \leq rdsd_{n,s} \hat{g}_{n,s} \cdot u_{n,s,t-1} - (rdsd_{n,s} \hat{g}_{n,s} - rd_{n,s,t} \hat{g}_{n,s}) \cdot u_{n,s,t} \\ - (\underline{g}_{n,s,t} \hat{g}_{n,s} + rd_{n,s,t} \hat{g}_{n,s} - rdsd_{n,s} \hat{g}_{n,s}) \cdot su_{n,s,t} \end{gather*}\]

Constraint Link-com-p-before:

\[\begin{gather*} f_{l,t-1} \leq rdsd_{l} \hat{f}_{l} \cdot u_{l,t-1} + (\bar{f}_{l,t} \hat{f}_{l} - rdsd_{l} \hat{f}_{l}) \cdot (u_{l,t} - su_{l,t}) \end{gather*}\]

Constraint Link-com-p-current:

\[\begin{gather*} f_{l,t} \leq \bar{f}_{l,t} \hat{f}_{l} \cdot u_{l,t} - (\bar{f}_{l,t} \hat{f}_{l} - rusu_{l} \hat{f}_{l}) \cdot su_{l,t} \end{gather*}\]

Constraint Link-com-partly-start-up:

\[\begin{gather*} f_{l,t} - f_{l,t-1} \leq (\underline{f}_{l,t} \hat{f}_{l} + ru_{l,t} \hat{f}_{l}) \cdot u_{l,t} - \underline{f}_{l,t} \hat{f}_{l} \cdot u_{l,t-1} \\ - (\underline{f}_{l,t} \hat{f}_{l} + ru_{l,t} \hat{f}_{l} - rusu_{l} \hat{f}_{l}) \cdot su_{l,t} \end{gather*}\]

Constraint Link-com-partly-shut-down:

\[\begin{gather*} f_{l,t-1} - f_{l,t} \leq rdsd_{l} \hat{f}_{l} \cdot u_{l,t-1} - (rdsd_{l} \hat{f}_{l} - rd_{l,t} \hat{f}_{l}) \cdot u_{l,t} \\ - (\underline{f}_{l,t} \hat{f}_{l} + rd_{l,t} \hat{f}_{l} - rdsd_{l} \hat{f}_{l}) \cdot su_{l,t} \end{gather*}\]

These constraints are defined in the function define_operational_constraints_for_committables().

Examples

  • Unit Commitment


    Models generator unit commitment with start-up and shut-down costs, ramping limits, minimum part loads, up and down times using binary variables.

    Go to example

  • Negative Prices in Linearized Unit Commitment


    Demonstrates how negative electricity prices emerge in linearized unit commitment when generators face high cycling costs and prefer to stay online at negative prices.

    Go to example


  1. J.A. Taylor (2015), Convex Optimization of Power Systems, Cambridge University Press, Chapter 4.3. ↩

  2. B. Hua, R. Baldick and J. Wang (2018), Representing Operational Flexibility in Generation Expansion Planning Through Convex Relaxation of Unit Commitment, IEEE Transactions on Power Systems, 33, 2, 2272-2281, doi:10.1109/TPWRS.2017.2735026, equations (21-24). ↩↩